Citywide Street Rehabilitation and Maintenance Project (FY 2022-24)
Each year, the City performs an annual citywide street rehabilitation and maintenance project, prioritizing various streets within the City for reconstruction, re-pavement, or slurry seal, in accordance with the City’s 5-Year Pavement Management Program. The Project improved 61 street segments, including 27 street segments rated 25 or below on the Pavement Condition Index (PCI). The Project was bid in the Fall of 2024 and awarded on November 19, 2024. The Project is funded using Senate Bill 1, TransNet, General Fund, and American Rescue Plan Act (ARPA) funds. Details regarding the project are as follows:
Contractor: Eagle Paving
Construction Cost: $3.9 M
Construction Commencement: January 2025
Estimated Completion Date: May 2026
Project Improvement Summary:
- 957,354 Square Feet of Slurry
- 2,026,862 Square Feet of Mill and Overlay
Selected Streets: (coming soon)
|
|
|
|
|
*SCHEDULE MAY BE IMPACTED DUE TO WEATHER