The City of Lemon Grove, in partnership with SDG&E, will soon begin construction to improve the community skyline by removing overhead utility poles and moving utility lines underground. Work will take place on Olive Street between Broadway and Highway 94 and North Avenue from Allison Lane to Grove Street.

 The Utility Undergrounding Project will support SDG&E’s continued efforts to provide clean, safe and reliable energy to serve the existing and future electricity needs of the residents and businesses in the area.

Construction start date is set for October 21, 2019. Construction will include trenching and conduit installation. The delay in the construction start date should not affect the Fall 2020 completion date.

An information meeting was held on Thursday, July 18 at the Lemon Grove Community Center. If you missed the meeting, you can view the information here.

Underground Informational flyer

 

Tentative Schedule

Location

Segment

Start

Complete

Mobilize

 

10/21/2019

 

Allison Lane

 

10/22/2019

10/30/2019

North Ave

Allison Lane to Olive Street

10/31/2019

11/5/2019

Olive Street

 

11/6/2019

12/3/2019

North Ave

Olive St to West side of Tracks

12/4/2019

2/4/2019

East side of Tracks to Grove St

 

2/5/2020

4/7/2020

North Ave Intersections (Night Work)

Lemon Grove Ave/Lemon Grove Way

4/29/2020

5/6/2020

Grind and Cap

 

5/1/2020

5/6/2020

Striping (Entire night work)

 

5/7/2020

5/8/2020